A checkpoint is seen at a bridge leading to the Unist’ot’en camp on a remote logging road near Houston, B.C., on January 17, 2019. A natural gas pipeline project has polarized many communities across northern British Columbia in a dispute a Wet’suwet’en elder says he hopes will be resolved through dialogue. Coastal GasLink is building the 670-kilometre pipeline from British Columbia’s northeast to Kitimat on the coast. The company has signed agreements with all 20 elected First Nation councils along its path, but the hereditary clan chiefs who are leaders under the traditional form of governance say the project has no authority without their consent. Darryl Dyck / The Canadian Press

CAN - B.C. Orders Coastal GasLink to Stop Pipeline Construction Near Protected Wetlands

The 670-kilometre pipeline is planned to transport natural gas from northeast B.C. to Kitimat

Coastal GasLink has been forced to stop pipeline construction near protected wetlands after an inspection by the B.C. Environmental Assessment Office found the company cleared areas without completing the required surveying and planning.

Coastal GasLink was issued two non-compliance orders in June and now has to complete the surveys before the project can proceed in the affected areas.

The 670-kilometre pipeline is planned to transport natural gas from northeast B.C. to Kitimat, for shipment to markets in Asia.

Wet’suwet’en Hereditary Chiefs served Coastal GasLink with an eviction notice on Jan. 4, starting a chain of events that led to RCMP enforcing a court-ordered injunction to arrest more than 80 protesters in February, including elders, chiefs and matriarchs. On June 5, charges against 22 Wet’suwet’en members and supporters were dropped and many others were never charged.